Catalyst with Shayle Kann
Catalyst with Shayle Kann

When to colocate data centers with generation

The idea of colocating data centers with behind-the-meter generation is picking up steam, including large projects in Memphis, Texas, and Utah developing significant on-site capacity, mostly from combined-cycle gas plants. The main argument is speed to power. Building your own generation allows data

Featured Speakers

Brian Janice Guest

Topics Discussed

Episode Summary

Executive Summary: The episode examines the surge of behind-the-meter power for data centers and argues that most on-site generation hype is overstated. Brian Janice says near-term nuclear won’t fit data center needs, while gas, storage, transmission upgrades, flexibility, and VPPs can often solve the real constraint: getting capacity delivered faster and more reliably.

Main Topics: Why data centers need power flexibility, not just energy (Priority: 5/5): The discussion centers on the distinction between needing 24/7 energy and needing enough capacity during peak conditions. Janice argues utilities solve for peak reliability, not full-year baseload matching. The limits of behind-the-meter generation (Priority: 5/5): On-site generation already exists as backup, but using it as primary power faces gas supply constraints, permitting issues, overbuild costs, and reliability complications. Time to power versus true economics (Priority: 4/5): Co-located generation is attractive because it may shorten the wait for interconnection, but Janice argues it usually raises power costs and may not beat grid-connected alternatives. Grid orchestration as the real solution (Priority: 5/5): The conversation highlights a portfolio approach: transmission, storage, grid-enhancing technologies, demand response, and VPPs could collectively unlock more data center load than isolated behind-the-meter projects. Why nuclear is unlikely to work behind the meter soon (Priority: 5/5): Janice is bullish on nuclear generally, but says new nuclear won’t solve data center timing, cost, or reliability needs quickly enough to justify co-location in the next couple of decades. The challenge of scaling coordinated programs (Priority: 4/5): Even if a better grid-based solution exists, it requires coordination across utilities, RTOs, and market rules—making execution and standardization the hardest part. Niche cases where on-site generation can help (Priority: 3/5): The guests note that some large campuses may use on-site generation or renewables to reduce grid draw below interconnect limits, especially in space-rich regions like West Texas.

Key Arguments: Data centers still require very high availability, because AI and cloud workloads cannot tolerate surprise outages; training can be flexible, but operators prefer planned downtime over unplanned interruptions. The default architecture remains grid connection plus UPS plus backup generators, and that is already a form of on-site generation for most cloud data centers. Behind-the-meter generation is often justified by speed to power, but the same problem may be solvable by grid-side flexibility, transmission, storage, or demand response. Off-grid gas generation is rarely cheaper once you include overbuild, redundancy, gas-grid constraints, and high capital cost per kilowatt. ERCOT scarcity pricing has fallen because of solar and storage, weakening the economic case for baseload-style private generation. The grid problem is primarily a capacity problem, not an energy problem; utilities focus on the hottest summer day and coldest winter morning rather than all 8,760 hours. Transmission and storage can substitute for some new generation by moving power through space and time, reducing the need for behind-the-meter plant buildout. A VPP-based bridging model could allow data centers to connect sooner if utilities accept aggregated flexibility as accredited capacity. Nuclear is power-dense, but new reactors are too slow, too uncertain, and too unproven for immediate co-location with data centers. The most realistic near-term case for on-site generation is reducing a project’s grid demand to fit within an existing interconnection limit, not going fully off-grid.

Data Points: Estimated on-site flexible capacity from devices: 3.4 gigawatts - Energy Hub’s VPP platform aggregates 2.5 million customer devices into dispatchable capacity. Customer devices aggregated: 2.5 million - Described as the scale of devices participating in Energy Hub’s virtual power plant. Thermostats, batteries, and EVs shifting load: Millions - Mentioned as devices that shifted energy during May and June peak periods. Backup outage duration that UPS bridges: Seconds to minutes - UPS is described as bridging short outages before generators take over. AI data center example size: 100 megawatts of IT - Used to illustrate how overbuilding for redundancy increases cost in an off-grid model. Example PUE: 1.2 - Applied to the 100 MW IT example to show total generation needs of about 120 MW before redundancy. Redundant generation add-on: 20-30 megawatts - Illustrative N+ redundancy added on top of the base load in the example. Average utilization relative to nameplate: 40-50% - A data center operator said actual annual utilization often falls well below theoretical peak capacity. Indicative capital cost: $2,700 per kW - Used to estimate the high cost of building on-site generation for a data center. Texas real-time power price: About $20/MWh - Used as the benchmark price for grid-connected electricity in ERCOT. Off-grid Texas power cost estimate: $150-$200/MWh - Estimated cost of self-supplied generation after overbuild and reliability considerations. Scarcity price in Texas historically: $5,000-$9,000/MWh - Referenced as the older ERCOT scarcity-spike rationale for baseload or dispatchable generation. Large data center examples: 1.3 GW and 1.4 GW - Examples in Port Washington, Wisconsin and Abilene illustrating the scale of recent AI/data center projects. Potential long interconnection timeline: 2038 - Referenced as an extreme example, likely in London, where on-site generation might make more sense. Potential capacity of a major new campus: 11 gigawatts - Mentioned as part of the Fermi project in Amarillo. Nuclear timeline outlook: Next couple of decades - Brian Janice says behind-the-meter nuclear is not credible in the near future.

Pivotal Quotes: "I don't think there's a credible argument for behind-the-meter nuclear at a data center in the near future." — Brian Janice: His core view on why co-located new nuclear does not solve data center power needs soon enough. "What we're trying to solve here is not that I need 24-7 generation to match a 24-7 load. It's that I need to solve for the summer peaks and the winter system peaks." — Brian Janice: Explains the difference between true grid planning and the simplistic baseload-matching narrative. "If I can move more power over more space, I am reducing the need to have to generate that power on the other end of that congestion." — Brian Janice: Describes why transmission can substitute for local generation in meeting data center load.

Implications: Data center power strategy is shifting from simple on-site generation toward coordinated grid flexibility. Expect more interest in VPPs, storage, transmission, and utility partnerships, while behind-the-meter nuclear remains a long-shot near term.

🔓 Sign Up for Unlimited Episode Search

About Catalyst with Shayle Kann

View all episodes from Catalyst with Shayle Kann