Executive Summary: Tony Broff of Dora Partners describes a gas-turbine market strained by surging demand, especially from data centers seeking fast behind-the-meter power. The established OEMs remain heavily backlogged and are expanding cautiously, creating openings for smaller suppliers and new technologies. Broff sees some alternatives as viable, but questions solutions requiring many small units. He expects turbine demand to ease after 2028 while remaining healthy over the longer term.

Main Topics: Major OEM backlogs and delivery timelines: GE Vernova, Siemens Energy, and Mitsubishi Power have substantial turbine order books, with deliveries for new bookings generally pushed to 2030–2032. GE also reports slot reservations separately from firm orders. Capacity growth versus demand: The leading manufacturers are adding capacity, but their projected output may remain limited relative to fast-growing data-center power demand and competing global needs. Broff says they are cautious about overbuilding amid the possibility of an AI downturn. Smaller generators and reciprocating engines: Established suppliers such as Cummins and Generac are pursuing data-center demand, including sites with hundreds of small units. Broff says modularity can help reliability when large turbines are unavailable, but the number of units creates operational, maintenance, and logistics burdens. New turbine designs and alternative cycles: Startups developing turbines from scratch face substantial technical and commercialization risk, while supercritical CO2 systems may have a more attainable technology pathway and could become a viable, though limited-impact, alternative. Retrofitted aircraft engines and other entrants: Companies converting used aircraft engines for stationary power may be viable if they solve challenges such as replacing thrust-producing components and adapting combustion systems. ProEnergy takes a distinct approach by redesigning many internal engine components. Pricing and the market outlook: Turbine prices have risen sharply, potentially improving the long-term economics of new-unit sales for OEMs. Broff expects market activity to decline from around 2028 as demand normalizes and low-cost renewables continue to expand, but not to return to an unhealthy level.

Key Arguments: Broff projects 126–132 GW of gas-turbine orders in 2026, above his earlier 101 GW forecast and broadly in line with his upside scenario. The leading OEMs cannot quickly satisfy demand: their projected capacity additions are significant, but the three companies’ combined 2030 capacity is still only about 75 GW annually, before accounting for worldwide demand across multiple sectors. Small modular units can support reliability and bridge-power applications when grid connections or large turbines are delayed, but hundreds of units per site can create serious integration, operating, and maintenance challenges. Building a new gas turbine from the ground up is exceptionally difficult and may take a decade or more; Broff regards supercritical CO2 cycles as a more plausible alternative because their technology leap may be smaller. Retrofitting aircraft engines for stationary power is promising, provided entrants address technical differences between aircraft propulsion and power generation, including the fan and fuel system. High current prices may fall from roughly $1,900–$2,500/kW to $800–$900/kW, still above historical levels and potentially making new-unit sales a more durable source of OEM profit. Broff expects turbine orders to begin declining around 2028, but says even a worst-case outlook leaves activity above 2023 levels a decade later; renewables remain a key constraint because they are the lowest-cost source of electricity.

Data Points: Projected gas-turbine orders in 2026: 126–132 GW - Broff's current projection; he had previously forecast about 101 GW and says the market is tracking near his upside case of around 126 GW. GE Vernova firm orders and slot reservations: About 53 GW firm orders; approximately 63 GW in reservations - Broff's estimate; combined firm orders and reservations approach 120 GW. Siemens Energy backlog: About 70 GW - Broff's best estimate of the company's backlog. Mitsubishi Power backlog: About 35 GW - Broff's best estimate of the company's backlog. Expected delivery timing for new major-OEM turbine slots: 2030–2032 - Broff says some product lines are sold out for five years or more. Annual capacity projections by 2030: GE Vernova: 20 to 30 GW; Siemens Energy: 16 to 23 GW; Mitsubishi Power: nearly double its capacity - Broff's estimates of capacity increases; he says each of the three leading OEMs is projected to reach roughly 23–30 GW annually. Capacity of other established suppliers: 5 GW per year or less each - Broff contrasts smaller suppliers with the three leading OEMs. North American data-center capacity demand by 2030: About 150–160 GW - Broff's estimate of data-center demand, underscoring the scale of the supply challenge. Small generator units at some data-center sites: 500–800 units per site - Broff describes plans involving units under 3 MW and calls their deployment and management a logistics challenge. Common turbine size ranges: About 7–100+ MW; popular ranges include 14–17 MW, 25–35 MW, and 40+ MW - Broff describes sizes seeing data-center-related demand; he notes some especially large orders exceed 300 MW. Example linear-generator installation: 10 units; 2.5 MW total; about 6,000 square feet - Broff argues that the land footprint per megawatt can be much larger than for gas turbines. Price of turbines in the 20–35 MW range: About $1,900–$2,500 per kW currently; potentially $800–$900 per kW over time - Broff contrasts current elevated prices with his expected longer-term level. Historical price comparison: About $400–$500 per kW - Broff says prices for comparable units were around this level not long ago. Expected market turning point: Decline may begin around 2028 - Broff predicts turbine order activity will ease as the current surge normalizes.

Pivotal Quotes: "It's very, very difficult to design a gas turbine from the ground up, having never done it before, and then be successful." — Tony Broff: Explaining why he is skeptical that new, greenfield turbine manufacturers will quickly become successful. "Even in my worst-case scenario, 10 years from now, the megawatt order activity is still more than it was in 2023." — Tony Broff: Summarizing why he expects the gas-turbine industry to remain viable despite a forecast decline in demand. "The lowest cost source of electricity globally, not just in Asia, not just in Europe, but here in the United States as well." — Tony Broff: Describing why expanding renewables could eventually reduce gas-turbine order activity.

Implications: Data-center developers face costly, delayed turbine supply and may turn to diverse technologies, but alternatives have trade-offs in scale, maturity, and complexity. OEMs may benefit from elevated pricing, yet should avoid overexpansion as demand could cool after 2028 and renewables continue gaining ground.